Office of the State Engineer

Water right applications backlogged

Real public dataWater Resource Allocation Program (WRAP)
340Q4 FY26
No targetCurrent

Proposed target 296

Proposed target: not adopted. DFA staff draft: return the backlog to the FY25 year-end level OSE reported (296).

FY25 and FY27 targets: Executive Budget Recommendations (FY26, FY27), Table 6; FY27 is the recommended target, p. 101

Source check.The LFC Performance Report Card for Q3 FY26 (p. 63) prints the FY25 actual as 1,359; DFA's dashboard and the FY27 Executive Budget (Table 6, p. 101) print 296. The quarterly values (293 to 340) are DFA's.

Published value Proposed target
Values by period
PeriodActualState target
FY2025296–
FY2024395–
FY2023445–

FY26 by quarter

FY26 quarterly results from DFA's dashboard
QuarterResult
Q1 FY26 Jul–Sep 2025293
Q2 FY26 Oct–Dec 2025332
Q3 FY26 Jan–Mar 2026334
Q4 FY26 Apr–Jun 2026340