Department of Transportation

Percent of projects completed according to schedule

Real public dataProject Design and Construction
86%FY2026
Off trackCurrent

State target 88%

FY25 and FY27 targets: Executive Budget Recommendations (FY26, FY27), Table 6; FY27 is the recommended target, p. 128

Published value State target
Values by period
PeriodActualState target
FY2027–88%
FY202686%88%
FY202594%88%
FY202485%–
FY202389%–

FY26 by quarter

FY26 quarterly results from DFA's dashboard
QuarterResult
Q1 FY26 Jul–Sep 202588%
Q2 FY26 Oct–Dec 202588%
Q3 FY26 Jan–Mar 202678%
Q4 FY26 Apr–Jun 202690%